Contractors and paying subs on time.

c_land

Well-Known Member
Joined
Jul 14, 2016
Messages
1,756
Reaction score
3,660
If you're typically a subcontractor, what do you do to ensure you get paid in a timely fashion outside of leins/stop notices.

I have someone that owes me about $8,900.00. Some invoices are 120 days outstanding. I finally threaten with a stop notice and all of a sudden an email shows up that they are preparing a check along with telling me to "cool my jets". I thought I was being pretty cool for the past 4 months, but I guess that just isn't cool enough.



Is there a better way of doing this without being a dick?
 

Yellowboat

Well-Known Member
Joined
Dec 18, 2007
Messages
16,110
Reaction score
6,369
Serve them, works the best.


I have almost 400k that people owe me as a gc. Just went too court for one Monday, won, but still no money.
 

Bigbore500r

Well-Known Member
Joined
Apr 28, 2014
Messages
17,450
Reaction score
35,470
If you're typically a subcontractor, what do you do to ensure you get paid in a timely fashion outside of leins/stop notices.

I have someone that owes me about $8,900.00. Some invoices are 120 days outstanding. I finally threaten with a stop notice and all of a sudden an email shows up that they are preparing a check along with telling me to "cool my jets". I thought I was being pretty cool for the past 4 months, but I guess that just isn't cool enough.



Is there a better way of doing this without being a dick?

All depends, what is in your contract with the GC / owner ? If your PWP (paid when paid), it can take...well....a long time! Most of my projects are PWP and we see 60-90 day pay cycles as a result. Sometimes a stop notice is the only way to get them to quite abusing you, and dont feel bad - they are the ones holding on to your money and making interest off it / bankrolling there company. If I was going to file the stop notice, these would be my questions before doing so:
-Are they typically a good customer?
-Do they always pay this late, or is this isolated to a single project (meaning the PM on that job may be the issue, not the company in general)
-Is the value of what im about to file a stop notice for substantial, or is this small potatoes?

Sometimes you just need to go above that persons head and find out why the payments are coming late
 

Bigbore500r

Well-Known Member
Joined
Apr 28, 2014
Messages
17,450
Reaction score
35,470
Make sure your following the conditional waiver / unconditional waiver process to a T as well. Is there a billing process in place, or is it just "ill send you invoices as I complete stuff, you pay them when you get them"
 

c_land

Well-Known Member
Joined
Jul 14, 2016
Messages
1,756
Reaction score
3,660
Serve them, works the best.


I have almost 400k that people owe me as a gc. Just went too court for one Monday, won, but still no money.

I do not envy you, I have trouble sleeping at night with my much smaller issues.

I do have the finance charges added, didnt really seem to do anything to speed up the payment. I think I only use 1.5%. Maybe I'll increase that.
 

c_land

Well-Known Member
Joined
Jul 14, 2016
Messages
1,756
Reaction score
3,660
All depends, what is in your contract with the GC / owner ? If your PWP (paid when paid), it can take...well....a long time! Most of my projects are PWP and we see 60-90 day pay cycles as a result. Sometimes a stop notice is the only way to get them to quite abusing you, and dont feel bad - they are the ones holding on to your money and making interest off it / bankrolling there company. If I was going to file the stop notice, these would be my questions before doing so:
-Are they typically a good customer?
-Do they always pay this late, or is this isolated to a single project (meaning the PM on that job may be the issue, not the company in general)
-Is the value of what im about to file a stop notice for substantial, or is this small potatoes?

Sometimes you just need to go above that persons head and find out why the payments are coming late

Make sure your following the conditional waiver / unconditional waiver process to a T as well. Is there a billing process in place, or is it just "ill send you invoices as I complete stuff, you pay them when you get them"


Balfour Beatty is the prime, but I'm a sub to the grading contractor. I've set my terms at 30 days with no protest other than non payments.

I'm pretty new in dealing directly with contractors and the receiveables myself so all advice is appreciated.
 

Yellowboat

Well-Known Member
Joined
Dec 18, 2007
Messages
16,110
Reaction score
6,369
I do not envy you, I have trouble sleeping at night with my much smaller issues.

I do have the finance charges added, didnt really seem to do anything to speed up the payment. I think I only use 1.5%. Maybe I'll increase that.
In .a 1.5% a month
 

milkmoney

Well-Known Member
Joined
Apr 30, 2008
Messages
31,478
Reaction score
20,583
Continental oil pays 6 months out. I get my money every Friday or i won't work [emoji202]
And no , I don't work for continental oil
Sent from my SM-G930V using Tapatalk
 

NicPaus

Well-Known Member
Joined
Sep 15, 2010
Messages
13,038
Reaction score
12,513
Commercial 60-90 days thats why you should have a lot of capital.

I only do residential usually get paid within a week. But have a few regulars that take about 30 to pay. I think I only have 1 currently passed a month but I have only made 1 effort to collect. Another 2 waiting to close escrow then I will get a check.


Until you build up Capital those sleepless nights will be there. I lose sleep when I hit 40-50K owed. Usually around $20-30K is where I am at. Some friends that have been around for a while usually $150k-250k owed at any given time.
 

boatpi

Well-Known Member
Joined
Feb 28, 2012
Messages
8,016
Reaction score
11,901
Are we speaking about contractors or boat builders..
 

LBLL

Low Budget Livin' Large
Joined
May 27, 2008
Messages
226
Reaction score
104
As a Commercial / Industrial GC we issue subcontracts as paid when paid. There are some of our customers / owner's that pay slightly late and others that tend to hold on for 45+ days blaming the lender. This is becoming more common. Main issues we have with sub billings is, they track aging based on the date their invoice is generated not the end of the month when we issue owner billings. Subs are requested to project billings based on projected work to be completed by the end of the month and dated the last day of the month and we as a GC bill the owner by the last day of the month. Typically, we get paid in 30+ to 45 days, so IF our sub is tracking their aging based on a billing they generated on the 15th, 30 days looks like 45 and 45 looks like 60. Most subs understand, but some do not and it becomes a constant drag, so we drop them or they drop us.
 

c_land

Well-Known Member
Joined
Jul 14, 2016
Messages
1,756
Reaction score
3,660
Commercial 60-90 days thats why you should have a lot of capital.

I only do residential usually get paid within a week. But have a few regulars that take about 30 to pay. I think I only have 1 currently passed a month but I have only made 1 effort to collect. Another 2 waiting to close escrow then I will get a check.


Until you build up Capital those sleepless nights will be there. I lose sleep when I hit 40-50K owed. Usually around $20-30K is where I am at. Some friends that have been around for a while usually $150k-250k owed at any given time.

It's all a learning process I guess, I am pretty down on cash in this account and don't want to start new work because of it. I have yet to be paid from this client without first requesting a check. It's pretty tiring.

i'm used to seeing larger outstanding amounts for the civil design projects, but with public agencies i know i'll get paid on the exact day in the contract. This has just been an unknown.
 

UltraLucky

Well-Known Member
Joined
Oct 4, 2007
Messages
889
Reaction score
1,106
If you're typically a subcontractor, what do you do to ensure you get paid in a timely fashion outside of leins/stop notices.

I have someone that owes me about $8,900.00. Some invoices are 120 days outstanding. I finally threaten with a stop notice and all of a sudden an email shows up that they are preparing a check along with telling me to "cool my jets". I thought I was being pretty cool for the past 4 months, but I guess that just isn't cool enough.



Is there a better way of doing this without being a dick?
Every contractor and project is different. The paid when paid provision is predicated on them submitting items your invoicing for to the owner in a timely manner it also may be unenforceable in California if that is where you are working. The terms should be spelled out in your contract and don't be afraid to negotiate them. If your just starting out you can offer a discount for timely payments ie. 5% if paid with in 15 days of receipt. But the key is finding the right people to speak with and to contact them a regular basis (not just when they owe you money) in person or on the phone. If it is a Public works project find out who the contract manager is for the owner they can be very helpful if the contractor is unresponsive.
 

c_land

Well-Known Member
Joined
Jul 14, 2016
Messages
1,756
Reaction score
3,660
As a Commercial / Industrial GC we issue subcontracts as paid when paid. There are some of our customers / owner's that pay slightly late and others that tend to hold on for 45+ days blaming the lender. This is becoming more common. Main issues we have with sub billings is, they track aging based on the date their invoice is generated not the end of the month when we issue owner billings. Subs are requested to project billings based on projected work to be completed by the end of the month and dated the last day of the month and we as a GC bill the owner by the last day of the month. Typically, we get paid in 30+ to 45 days, so IF our sub is tracking their aging based on a billing they generated on the 15th, 30 days looks like 45 and 45 looks like 60. Most subs understand, but some do not and it becomes a constant drag, so we drop them or they drop us.

That is helpful. Going forward I'll try to align my billing cycles with my client contractor or GC.
 

Yellowboat

Well-Known Member
Joined
Dec 18, 2007
Messages
16,110
Reaction score
6,369
Get use too it. I had one last year that was 17 months behind and got a random check in the mail. I was not expecting that.
 

NicPaus

Well-Known Member
Joined
Sep 15, 2010
Messages
13,038
Reaction score
12,513
It's all a learning process I guess, I am pretty down on cash in this account and don't want to start new work because of it. I have yet to be paid from this client without first requesting a check. It's pretty tiring.

i'm used to seeing larger outstanding amounts for the civil design projects, but with public agencies i know i'll get paid on the exact day in the contract. This has just been an unknown.


I hear you I hate having to ask when they know they owe. Some are just that way you have to hound them constantly. I usually quit doing work for those types but when starting up you can't pass up work. Get your Contracts written with pay schedules clearly stated will help. I like my regular customers where we just get it done and get paid when finished but it took me 10 years to establish the relationship with them where we are on the same page. Not easy but hard work always pays off.
 

ROZ

Well-Known Member
Joined
Oct 3, 2007
Messages
2,234
Reaction score
76
If you're typically a subcontractor, what do you do to ensure you get paid in a timely fashion outside of leins/stop notices.

I have someone that owes me about $8,900.00. Some invoices are 120 days outstanding. I finally threaten with a stop notice and all of a sudden an email shows up that they are preparing a check along with telling me to "cool my jets". I thought I was being pretty cool for the past 4 months, but I guess that just isn't cool enough.



Is there a better way of doing this without being a dick?

I don’t think threatening a stop work notice after not being paid for up to 120 days in some cases is being a dick.

I don’t know details, but my wife worked on a case where a contractor literally walked off a job over some type of dispute. Property owner sues and won. So cover your ass with plenty of notes , dates, and emails of contact with your client if you decide to cut your ties.



Sent from my iPhone using Tapatalk
 

mash on it

Beyond Hell Crew
Joined
Jan 26, 2011
Messages
3,641
Reaction score
5,451
My invoices have '1% 10 days NET 30'
I also bill accounts receivable the next day via email. 'Signed Copy on File' in there too.
At 30 days, I email them with an invoice, and then every week. I can't bankroll a $40 million company, and won't. It's only a grand or two, but it's my paycheck.
90 days? They can kiss my ass. How's C.O.D. then? But I'm not a 'contractor'.

Dan'l
 

DaveC

Car-boat motors
Joined
Sep 25, 2007
Messages
11,177
Reaction score
6,350
Wait! You mean to tell me there are some GC that pay on time? Who knew
 

ChumpChange

Commercial Banker
Joined
Dec 19, 2007
Messages
9,708
Reaction score
10,833
Get use too it. I had one last year that was 17 months behind and got a random check in the mail. I was not expecting that.

The stories you tell.......

To all the GC out there......Dont ask your subs to finance your jobs.

Why ask when you can just DO! It's not just contracting, it's business. From the small company getting terms from their vendors to the giants like WalMart. I remember it was just about five years ago, WalMart sent out a letter to their suppliers that their terms were being extended from 60 to 90 days. Do you know how much cash that freed up for WalMart? Product doesn't sit on the shelf that long. Sells in five days, they collect the cash, and now have another 85 days to use as operating capital. It put a big hurt on their suppliers though, needing lines of credit to finance those terms.
 

River Lynchmob

What can I do to u for u?
Joined
Sep 21, 2007
Messages
13,252
Reaction score
9,311
The stories you tell.......



Why ask when you can just DO! It's not just contracting, it's business. From the small company getting terms from their vendors to the giants like WalMart. I remember it was just about five years ago, WalMart sent out a letter to their suppliers that their terms were being extended from 60 to 90 days. Do you know how much cash that freed up for WalMart? Product doesn't sit on the shelf that long. Sells in five days, they collect the cash, and now have another 85 days to use as operating capital. It put a big hurt on their suppliers though, needing lines of credit to finance those terms.
One of the infinite reasons I hate Walmart.
 

500bbc

Well-Known Member
Joined
Oct 16, 2007
Messages
26,501
Reaction score
40,407
When not prime contractor I make sure twenty day notice is filed, past due notices sent, lien filed within the specified time frame then perfected if need be.
Had a developer try to stiff us for over $150,000.00, the retention, until they needed take out.:D

They fucked a bunch of poor sons of bitches.

Just liened a residential asshole a couple of months ago, he was trying to stall me past the filing time frame. Fucking attorney.
 

rivergames

Well-Known Member
Joined
Jan 7, 2008
Messages
15,850
Reaction score
13,082
Gotta check up on the billing each month. After a few months of not getting paid, then you hammer the GC a few times a week for updates. If still no payment, time to drop the liens and stop notices.

Don't get too comfortable/relaxed and always watch where your $ is or will be.
 

Boat 405

Well-Known Member
Joined
Dec 20, 2007
Messages
4,462
Reaction score
8,039
If you're typically a subcontractor, what do you do to ensure you get paid in a timely fashion outside of leins/stop notices.

I have someone that owes me about $8,900.00. Some invoices are 120 days outstanding. I finally threaten with a stop notice and all of a sudden an email shows up that they are preparing a check along with telling me to "cool my jets". I thought I was being pretty cool for the past 4 months, but I guess that just isn't cool enough.



Is there a better way of doing this without being a dick?


Progress payments.
 

KENDOG689

Banned
Joined
Feb 22, 2011
Messages
4,033
Reaction score
3,816
Had a general I was working for and did take him to court.Was agreed to be paid in a year in payments.5yrs later.....I still get a small check.:(
 

KENDOG689

Banned
Joined
Feb 22, 2011
Messages
4,033
Reaction score
3,816
Must be nice, CA we can only get 10% down and no more than a $1000.
Yes I know that in Ca,but finding a reliable framer here is like a needle in a hay stack.I worked for a guy that would ask for 50% upfront and always got it.Covered his cost but the other 50 was always slow pay.
 

NicPaus

Well-Known Member
Joined
Sep 15, 2010
Messages
13,038
Reaction score
12,513
Yes I know that in Ca,but finding a reliable framer here is like a needle in a hay stack.I worked for a guy that would ask for 50% upfront and always got it.Covered his cost but the other 50 was always slow pay.
10%Down 40% when material deliered. 40% when last materials dropped 10% upon completion this works out better than 2 payments
 

KENDOG689

Banned
Joined
Feb 22, 2011
Messages
4,033
Reaction score
3,816
Kinda different here.Most GCs supply the material and labor only.The lumber is always paid but that is why you bill for more upfront.All these fuckers learned how to do it in CA.Gotta play the game better.
 

locogringo

Yo Mama
Joined
Dec 27, 2007
Messages
733
Reaction score
398
Do mostly commercial roofing and related items, run our own crews and building a larger residential end now as well.

On commercial: 20% upon contract signing, 50% upon material delivery and commencement of work, then final 30% upon sign off of job.

Never had a problem on the commercial end.

Residential end has been good so far too.

Now, when subbing out work to GC’s: So far so good for all except one who is 60 days currently.

Progress payments is the only way to go and if you are able to, minimize sub-contracting work as much as possible.
 